Hardware Form / Build guides / EVT · DVT · PVT
Build guide

EVT vs DVT vs PVT

Teams mix these gates. Factories then discover thermal or vision drift that EVT should have caught.

EVT proves the integrated prototype works. DVT proves the frozen design across units and stress. PVT (pilot production) proves the line can build to spec. AI hardware adds inference load, camera lot variation, and OTA rollback to each gate.

GateQuestionAI-specific checks
EVTDoes it work?Thermal under GPU load, sync, model pin
DVTDoes the design meet spec?Multi-unit vision spread, vibe/drop class
PVTCan the line build it?Yield, EOL test = EVT scripts

Related: EVT/DVT checklist · NPI

One accountable program from architecture through production. Hardware Form runs ISO 9001 and ISO 13485 quality systems with BSCI supply-chain compliance. We have taken products through UL as part of client programs; listings remain product-specific.

Operations scale with roughly 400 staff across engineering and manufacturing. See quality and certifications.

01

Define

Requirements, risks, and evidence for the next build gate.

02

Build

Integrated prototypes with production-relevant materials and test.

03

Validate

Functional, environmental, and manufacturing readiness checks.

04

Scale

NPI, yield tracking, and controlled ramp on our lines.